The preliminary work is nearly complete- including curb ramps, curb extensions, and sidewalks. The paving is underway with most paving scheduled for completion the week of January 8. Two special cases will be paved at the end of the month- North and South Blanche Street and Mallory Way. The schedule is subject to delay due to weather.